DULCIE PERRY RESERVE IRRIGATION PUMP STATION

Dulcie Perry Reserve, Cecelia St & Day St, NORTH BRIGHTON, South Australia, Australia. 5048

Estimated Value $150,000

Development Irrigation pump station

Main Category Public utilities

  • Early Planning
  • Planning
  • Tenders
  • Construction

About This Project


The Principal invites tenders for provision of the following: The work included in this contract comprises the provision of all labour, plant, tools & materials & includes but is not limited by the following: 1) Location & protection of existing infrastructure; 2) Supply & installation of 5,000 L in ground concrete tank (R.I. Industries or equivalent); 3) Supply & install a Lowara SCUBA SC411C single phase submersible pump with float switch; 4) Supply & install DN90 overflow to the closest stormwater pit. The overflow is to be set at a level to provide an air gap as per AS3500 registered air gap; 5) Supply & install all required isolation, non-return, master & float valves; 6) Supply & install power from nearest suitable service to new control panel; 7) Supply & install new motor control panel incorporating the existing irrigation controller; 8) Supply & install two DN63 PE100 PN12.5 pipelines. Pipeline from the water meter to the tank is to be Blueline. Pipeline from the tank to the irrigation system is to be Lilac; 9) Clean up the site to match existing levels; 10) Commission the pump & irrigation system; 11) Arrange for a Practical Completion inspection & operation demonstration; & 12) Provide as contracted drawings & documentation as specified.

Full information about DULCIE PERRY RESERVE IRRIGATION PUMP STATION and other development projects are available with the Cordell Connect subscription

Subscription includes
  • Full access to over 160,000 development projects
  • Over 63,000 industry contacts
  • 1500 hours of research every week
Further Information

Details available with subscription

Start A Free Trial
Type IRRIGATION PUMP STATION
Dev Type New
Status Commenced
Stage COMPLETED
Ownership 4
No. Units 0.000
No. Floors 0.000
Commencement Date 05/06/17
Completion Date 14/07/17
First Reported Date 03/05/17

Project Information

Roles

Get full contact details for those working on the project at this stage

Consulting Engineer
Developer
Pam Andritsakis
Tendering Authority
Pam Andritsakis
Contractor
Tenderer

Get full contact details for 1 tenderers on this project

Tenderer

Other Projects

Stay Connected with Cordell Connect

Cordell Connect tracks the lifespan of all Construction, Civil & Mining projects across Australia, naming key roles as they are appointed. This allows you to target and track projects & companies you would like to get involved with and is your one-stop shop for target sales leads in construction.