HAT HEAD SEWAGE TREATMENT PLANT

., HAT HEAD, New South Wales, Australia. 2440

Estimated Value $1 million

Development Treatment plant - augmentation

Main Category Public utilities

  • Early Planning
  • Planning
  • Tenders
  • Construction

About This Project


Scope of work includes: removal & disposal of existing interim pipework concrete works, supply & installation of a sewage return pump station, supply & installation of balance tank pipework, supply & installation of steel walkway platforms.

Full information about HAT HEAD SEWAGE TREATMENT PLANT and other development projects are available with the Cordell Connect subscription

Subscription includes
  • Full access to over 160,000 development projects
  • Over 63,000 industry contacts
  • 1500 hours of research every week
Further Information

Details available with subscription

Request Demo
Type TREATMENT PLANT - augmentation
Dev Type New
Status Commenced
Stage CONSTRUCTION
Ownership 4
No. Units 0.000
No. Floors 0.000
Commencement Date 15/11/17
Completion Date 19/08/18
First Reported Date 30/08/17

Project Information

Roles

Get full contact details for those working on the project at this stage

Developer
Bala Vigneswaran
Tendering Authority
Bala Vigneswaran
Engineer
Contractor
Tenderer

Get full contact details for 5 tenderers on this project

Tenderer
Tenderer
Tenderer
Tenderer
Tenderer

Other Projects

Stay Connected with Cordell Connect

Cordell Connect tracks the lifespan of all Construction, Civil & Mining projects across Australia, naming key roles as they are appointed. This allows you to target and track projects & companies you would like to get involved with and is your one-stop shop for target sales leads in construction.