MARGARET RIVER PERIMETER ROAD WORKS - STAGE 2

Margaret River Perimeter Rd, MARGARET RIVER, Western Australia, Australia. 6285

Estimated Value $22.817 million

Development Roadworks/bridgeworks - stage 2

Main Category Civil engineering

  • Early Planning
  • Planning
  • Tenders
  • Construction

About This Project


Construction of a 5.2 km two lane carriageway with major roundabouts at the northern & southern intersections with Bussel Highway on Margaret River Perimeter Road in Stage 2 & to comprise of: revitalisation of the main street precinct, extension of John Archibald Drive & road completion works. The project will also include construction of new traffic & pedestrian bridge across Margaret River & another 2.2 km of road connecting John Archibald Drive to perimeter road.

Full information about MARGARET RIVER PERIMETER ROAD WORKS - STAGE 2 and other development projects are available with the Cordell Connect subscription

Subscription includes
  • Full access to over 160,000 development projects
  • Over 63,000 industry contacts
  • 1500 hours of research every week
Further Information

Details available with subscription

Request Demo
Type ROADWORKS/BRIDGEWORKS - stage 2
Dev Type Addition
Status Commenced
Stage CONSTRUCTION
Ownership 3
No. Units 0.000
No. Floors 0.000
Commencement Date 28/08/17
Completion Date 04/06/18
First Reported Date 13/05/15

Project Information

Roles

Get full contact details for those working on the project at this stage

Tendering Authority
Developer
Reece Waldock
Civil Engineer
Consultant
Project Manager
John Szeliga
Contractor
Contractor

Other Projects

Stay Connected with Cordell Connect

Cordell Connect tracks the lifespan of all Construction, Civil & Mining projects across Australia, naming key roles as they are appointed. This allows you to target and track projects & companies you would like to get involved with and is your one-stop shop for target sales leads in construction.